This question asks us to find B's daily work rate when the total job can be completed in 15 days.
Work rate is the fraction of total work completed per day.
Since B completes the entire job, the total work equals 1.
B completes the job in 15 days, so divide the work by the number of days.
B's work rate is 1/15 of the job per day, which means B completes one-fifteenth of the job each day for 15 days to finish it completely.
This question tests the concept of work rate and how much work is completed in a given time period.
A completes the entire work in 20 days, so the work rate is 1 part per day.
Multiply the daily work rate by the number of days.
Reduce the fraction to its simplest form by dividing both numerator and denominator by 5.
A will complete 1/4 of the work in 5 days.