Home Subjects Quantitative Aptitude Time and Work

Quantitative Aptitude
Time and Work

Quantitative aptitude questions for competitive exams

23 Q 7 Topics Take Mock Test
Advertisement
Difficulty: All Easy Medium Hard 21–23 of 23
Topics in Quantitative Aptitude
Q.21 Hard Time and Work
A contractor agrees to build a bridge in 300 days. He employs 10 workers. After 150 days, he finds that only half the work is complete. How many additional workers does he need to finish on time?
A 5 workers
B 10 workers
C 15 workers
D 20 workers
Correct Answer:  B. 10 workers
EXPLANATION

Remaining days = 150. Remaining work = 1/2. Current productivity = (1/2 work)/(150 days × 10 workers) = 1/3000 per worker-day. Required rate = (1/2)/(150 × x) where x is total workers. x = 10. So need 10 additional workers.

Test
Q.22 Hard Time and Work
A, B, and C can complete a work in 6 days, 8 days, and 12 days respectively. A and B work for 2 days, then C joins them. How many more days will they take to complete the remaining work?
A 1.5 days
B 2 days
C 2.5 days
D 3 days
Correct Answer:  B. 2 days
EXPLANATION

A+B rate = 1/6 + 1/8 = 7/24.

Work in 2 days = 14/24 = 7/12.

Remaining = 5/12.

All three rate = 1/6 + 1/8 + 1/12 = 9/24 = 3/8.

Days = (5/12)/(3/8) = 40/36 ≈ 1.11, recalculating: remaining work done in 2 days

Test
Q.23 Hard Time and Work
If A works for 3 days and B works for 2 days, they complete 1/4 of work. If A works for 2 days and B works for 3 days, they complete 1/3 of work. How many days does A take to complete the work alone?
A 30 days
B 25 days
C 20 days
D 15 days
Correct Answer:  A. 30 days
EXPLANATION

Let A's rate = 1/x, B's rate = 1/y.

From equations: 3/x + 2/y = 1/4 and 2/x + 3/y = 1/3.

Solving: x = 30 days

Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips