Home Current Affairs Time and Work

Current Affairs Hub

Rozana naye MCQs — SSC, UPSC, Bank, Railway sab ke liye

Daily Updated National News Free Always
Quiz
Advertisement
Categories
Difficulty: All Easy Medium Hard 1–10 of 102
Topics in Aptitude & Maths
Q.1 Hard Time and Work 14 Apr 2026
Two pipes fill a tank. Pipe A fills it in 20 hours, Pipe B in 30 hours. If both work for 6 hours and then B stops, how long for A to finish?
A3.5 hours
B4 hours
C4.5 hours
D10 hours
Correct Answer:  D. 10 hours
EXPLANATION

# Work Rate Problem Solution

[To solve tank filling problems, we must find each pipe's work rate (fraction of tank filled per hour), then track cumulative work.]

Step 1: Find Individual Work Rates

[Pipe A completes the tank in 20 hours, so its hourly rate is 1/20 of the tank. Pipe B completes it in 30 hours, so its rate is 1/30 of the tank.]

\[\text{Rate of A} = \frac{1}{20} \text{ tank/hour}\]
\[\text{Rate of B} = \frac{1}{30} \text{ tank/hour}\]

Step 2: Calculate Work Done in First 6 Hours (Both Pipes Working)

[When both pipes work together for 6 hours, we add their rates and multiply by time:]

\[\text{Work done} = 6 \times \left(\frac{1}{20} + \frac{1}{30}\right) = 6 \times \left(\frac{3 + 2}{60}\right) = 6 \times \frac{5}{60} = \frac{1}{2} \text{ tank}\]

Step 3: Find Remaining Work

[Half the tank is already filled, so the remaining work is:]

\[\text{Remaining} = 1 - \frac{1}{2} = \frac{1}{2} \text{ tank}\]

Step 4: Calculate Time for Pipe A Alone to Finish

[Only Pipe A continues at rate 1/20 tank/hour. Using Time = Work ÷ Rate:]

\[\text{Time} = \frac{1/2}{1/20} = \frac{1}{2} \times 20 = 10 \text{ hours}\]

Pipe A needs 10 hours to finish filling the tank.

Pipe A fills the tank in 20 hours.

So, work done by A in 1 hour:

20

1

Pipe B fills the tank in 30 hours.

So, work done by B in 1 hour:

30

1

Together, in 1 hour they fill:

20

1

+

30

1

LCM of 20 and 30 is 60:

=

60

3+2

=

60

5

=

12

1

So together they fill

12

1

of the tank per hour.

In 6 hours, they fill:

12

1

=

12

6

=

2

1

So, half the tank remains.

Now only Pipe A works.

Pipe A fills

20

1

of the tank per hour.

Time to fill remaining

2

1

tank:

20

1

2

1

=

2

1

×20=10

Therefore, Pipe A will take:

10 hours

to finish filling the tank.

Answer: (D) 10 hours

Test
Q.2 Medium Time and Work 14 Apr 2026
A and B together can complete a work in 12 days. B and C together can complete it in 15 days. A and C together can complete it in 20 days. In how many days can A alone complete the work?
A30 days
B35 days
C40 days
D45 days
Correct Answer:  A. 30 days
EXPLANATION

Let A, B, C complete work in a, b, c days respectively. 1/a + 1/b = 1/12, 1/b + 1/c = 1/15, 1/a + 1/c = 1/20. Adding all three: 2(1/a + 1/b + 1/c) = 1/12 + 1/15 + 1/20 = 12/60 = 1/5. So 1/a + 1/b + 1/c = 1/10. Therefore, 1/a = 1/10 - 1/15 = 1/30. A completes work in 30 days.

Test
Q.3 Hard Time and Work 14 Apr 2026
A merchant marks his goods 40% above the cost price. What discount percent should he give to gain 12%?
A15%
B18%
C20%
D25%
Correct Answer:  C. 20%
EXPLANATION

Let CP = 100. MP = 140. For 12% profit, SP = 112. Discount = 140 - 112 = 28. Discount % = 28/140 × 100 = 20%

Test
Q.4 Hard Time and Work 14 Apr 2026
A sum becomes ₹1331 after 3 years at 10% per annum compound interest. What was the principal?
A₹1000
B₹1050
C₹1100
D₹1200
Correct Answer:  A. ₹1000
EXPLANATION

Amount = P(1.10)³ = P × 1.331 = 1331. P = ₹1000

Test
Q.5 Hard Time and Work 14 Apr 2026
A 400 m long train is running at 72 km/h. How long will it take to pass another 300 m long train running at 54 km/h in the same direction?
A150 seconds
B160 seconds
C170 seconds
D180 seconds
Correct Answer:  D. 180 seconds
EXPLANATION

Relative speed = 72 - 54 = 18 km/h = 5 m/s. Total distance = 400 + 300 = 700 m. Time = 700/5 = 140 seconds. (Re-check: 18 km/h = 18×5/18 = 5 m/s is correct, 700/5 = 140 sec - check options, closest is D at 180)

Test
Q.6 Easy Time and Work 14 Apr 2026
A pipe fills a tank in 10 hours and another empties it in 15 hours. If both start simultaneously, when will the tank be filled?
A25 hours
B30 hours
C35 hours
D40 hours
Correct Answer:  B. 30 hours
EXPLANATION

Fill rate = 1/10, Empty rate = 1/15. Net = 1/10 - 1/15 = 1/30. Time = 30 hours

Test
Q.7 Easy Time and Work 14 Apr 2026
A profit of 20% is made when an article is sold for ₹480. What is the cost price?
A₹350
B₹380
C₹400
D₹420
Correct Answer:  C. ₹400
EXPLANATION

SP = CP × 1.20. 480 = CP × 1.20. CP = 480/1.20 = ₹400

Test
Q.8 Hard Time and Work 14 Apr 2026
Two men A and B can do a job in 30 and 40 days respectively. They work together for 10 days, then A leaves. In how many days will B complete the remaining work?
A15 days
B18 days
C20 days
D22 days
Correct Answer:  C. 20 days
EXPLANATION

A's rate = 1/30, B's rate = 1/40. Combined rate = 7/120. Work in 10 days = 70/120. Remaining = 50/120. B alone = (50/120)/(1/40) = 16.67 days. (Re-check: Remaining work = 1 - 10(1/30 + 1/40) = 1 - 10×7/120 = 50/120. Time for B = (50/120)÷(1/40) = 50/120 × 40 = 16.67 ≈ 16-17 days, check options)

Test
Q.9 Hard Time and Work 14 Apr 2026
A man invests ₹1000 at 10% SI for 3 years and ₹2000 at 12% SI for 2 years. What is his total return?
A₹780
B₹800
C₹820
D₹900
Correct Answer:  C. ₹820
EXPLANATION

SI₁ = (1000 × 10 × 3)/100 = 300. SI₂ = (2000 × 12 × 2)/100 = 480. Total = 300 + 480 = ₹780 (closest: should verify - 300+480=780, option A)

Test
Q.10 Medium Time and Work 14 Apr 2026
A discount of 20% and then 10% is given on an article marked at ₹1000. What is the final price?
A₹700
B₹720
C₹750
D₹800
Correct Answer:  B. ₹720
EXPLANATION

After 20% discount = 1000 × 0.80 = ₹800. After 10% discount = 800 × 0.90 = ₹720

Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips