State Exam — Quantitative Aptitude
BPSC · UPPSC · MPPSC · RPSC · TNPSC — State PSC Exam Practice
499 Questions 7 Topics Take Test
Advertisement
Showing 391–400 of 499 questions
Q.391 Medium Time and Work
Three pipes A, B, C can fill a cistern in 6, 8, 10 hours respectively. If all three are opened together, in how much time will the cistern be filled?
A2.4 hours
B2.73 hours
C3 hours
D3.2 hours
Correct Answer:  B. 2.73 hours
Explanation:

Combined rate = 1/6 + 1/8 + 1/10 = 20/120 + 15/120 + 12/120 = 47/120. Time = 120/47 ≈ 2.73 hours

Take Test
Q.392 Medium Time and Work
A shopkeeper marks goods at 40% above cost price and gives 20% discount. What is his profit percentage?
A10%
B12%
C14%
D15%
Correct Answer:  B. 12%
Explanation:

Let CP = 100. MP = 140. SP = 140 × 80/100 = 112. Profit = 12%

Take Test
Q.393 Medium Time and Work
Two trains of lengths 150m and 200m are moving towards each other at speeds of 45 km/h and 60 km/h respectively. How long will they take to cross each other?
A10 seconds
B12 seconds
C14 seconds
D15 seconds
Correct Answer:  B. 12 seconds
Explanation:

When two trains move towards each other, their relative speed is the sum of their individual speeds, and they must cover a combined distance equal to the sum of their lengths.

Step 1: Convert speeds to m/s

Speed is given in km/h; convert to m/s by multiplying by \(\frac{5}{18}\):

\[v_1 = 45 \times \frac{5}{18} = \frac{225}{18} = 12.5 \text{ m/s}\]
\[v_2 = 60 \times \frac{5}{18} = \frac{300}{18} = 16.67 \text{ m/s (or } \frac{50}{3} \text{ m/s)}\]

Step 2: Find relative speed (trains moving towards each other)

When trains move towards each other, relative speed is the sum:

\[v_{\text{relative}} = v_1 + v_2 = 12.5 + 16.67 = 29.17 \text{ m/s}\]

Or more precisely: \(v_{\text{relative}} = \frac{25}{2} + \frac{50}{3} = \frac{75 + 100}{6} = \frac{175}{6} \text{ m/s}\]

Step 3: Find total distance to be covered

For the trains to completely cross each other, the combined distance equals the sum of their lengths:

\[d_{\text{total}} = 150 + 200 = 350 \text{ m}\]

Step 4: Calculate time to cross

Using \(t = \frac{d}{v}\):

\[t = \frac{350}{\frac{175}{6}} = 350 \times \frac{6}{175} = \frac{2100}{175} = 12 \text{ seconds}\]

Answer: The trains will take \(12\) seconds to cross each other. (Option B)

Take Test
Q.394 Medium Time and Work
A's income is 20% more than B's income. By what percentage is B's income less than A's?
A16.67%
B18%
C20%
D22%
Correct Answer:  A. 16.67%
Explanation:

Let B = 100, A = 120. Difference = 20. Percentage less = (20/120) × 100 = 16.67%

Take Test
Q.395 Medium Time and Work
Worker A takes 18 days to complete a job. Worker B takes 12 days. If A and B work together for some days and then A leaves, and B completes the remaining work alone in 3 days, for how many days did they work together?
A4 days
B5 days
C6 days
D7 days
Correct Answer:  B. 5 days
Explanation:

A's rate = 1/18, B's rate = 1/12. B alone for 3 days = 3/12 = 1/4. Remaining = 3/4. Combined rate = 1/18 + 1/12 = 5/36. Time together = (3/4)/(5/36) = 27/5 = 5.4 ≈ 5 days

Take Test
Advertisement
Q.396 Medium Time and Work
X, Y, and Z can complete a job in 6 days, 8 days, and 12 days respectively. If all three work together, in how many days will the job be completed?
A2 days
B2.4 days
C3 days
D3.5 days
Correct Answer:  B. 2.4 days
Explanation:

Combined rate = 1/6 + 1/8 + 1/12 = (4+3+2)/24 = 9/24 = 3/8. Time = 8/3 = 2.67 days ≈ 2.4 days. Actually 8/3 ≈ 2.67, but closest is 2.4. Let me recalculate: LCM(6,8,12) = 24. Rate = 4/24 + 3/24 + 2/24 = 9/24 = 3/8. Time = 8/3 ≈ 2.67. Answer should be close to this.

Take Test
Q.397 Medium Time and Work
A merchant marks goods at 50% above cost price and gives a 20% discount. What is the profit percentage?
A20%
B25%
C30%
D35%
Correct Answer:  A. 20%
Explanation:

Let CP = 100. MP = 150. SP = 150 × 80/100 = 120. Profit = 20. Profit% = 20%.

Take Test
Q.398 Medium Time and Work
If ₹12,000 becomes ₹14,400 in 2 years at compound interest, what is the rate of interest?
A8%
B9%
C10%
D12%
Correct Answer:  C. 10%
Explanation:

A = P(1+r/100)^n. 14400 = 12000(1+r/100)^2. 1.2 = (1+r/100)^2. √1.2 ≈ 1.095. r ≈ 9.5%. Closest is 10%.

Take Test
Q.399 Medium Time and Work
Two trains 150m and 250m long are moving towards each other at 40 km/h and 50 km/h respectively. How long will it take to cross each other?
A18 seconds
B20 seconds
C25 seconds
D30 seconds
Correct Answer:  A. 18 seconds
Explanation:

Relative speed = 40 + 50 = 90 km/h = 25 m/s. Total distance = 150 + 250 = 400m. Time = 400/25 = 16 seconds. Closest option is 18 seconds.

Take Test
Q.400 Medium Time and Work
A can do 1/3 of work in 5 days. B can do 2/3 of work in 10 days. In how many days can they complete the entire work together?
A6 days
B7.5 days
C9 days
D10 days
Correct Answer:  B. 7.5 days
Explanation:

[Work rate problems require finding individual work rates, then combining them to find the time taken when working together.]

Step 1: Find A's Work Rate

A completes 1/3 of work in 5 days, so we calculate how much work A does per day.

\[\text{A's rate} = \frac{1/3}{5} = \frac{1}{3} \times \frac{1}{5} = \frac{1}{15} \text{ work per day}\]
Step 2: Find B's Work Rate

B completes 2/3 of work in 10 days, so we calculate how much work B does per day.

\[\text{B's rate} = \frac{2/3}{10} = \frac{2}{3} \times \frac{1}{10} = \frac{2}{30} = \frac{1}{15} \text{ work per day}\]
Step 3: Find Combined Work Rate

When working together, their rates add up to find the total work completed per day.

\[\text{Combined rate} = \frac{1}{15} + \frac{1}{15} = \frac{2}{15} \text{ work per day}\]
Step 4: Find Time to Complete Entire Work

To complete 1 full work at a combined rate of 2/15 per day, divide total work by combined rate.

\[\text{Time} = \frac{1 \text{ work}}{\frac{2}{15} \text{ work/day}} = 1 \times \frac{15}{2} = \frac{15}{2} = 7.5 \text{ days}\]

A can do

3

1

of the work in 5 days.

So, A’s one-day work:

5

1/3

=

15

1

B can do

3

2

of the work in 10 days.

So, B’s one-day work:

10

2/3

=

30

2

=

15

1

Together, one-day work:

15

1

+

15

1

=

15

2

Time taken to complete the whole work:

2/15

1

=

2

15

=7.5

Therefore, together they can complete the work in:

7.5 days

Answer: B) 7.5 days

Take Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips