State Exam — Quantitative Aptitude — Average
BPSC · UPPSC · MPPSC · RPSC · TNPSC — State PSC Exam Practice
22 Questions 7 Topics Take Test
Advertisement
Showing 1–10 of 22 questions in Average
Q.1 Medium Average
A boat travels 50 km upstream in 5 hours and 80 km downstream in 4 hours. What is the average speed of the boat in still water?
A15 km/h
B12.5 km/h
C14 km/h
D13.5 km/h
Correct Answer:  A. 15 km/h
Explanation:

Upstream speed = 50/5 = 10 km/h. Downstream speed = 80/4 = 20 km/h. Boat speed in still water = (10 + 20)/2 = 15 km/h.

Take Test
Q.2 Medium Average
The average of first n natural numbers is 10.5. What is the value of n?
A20
B21
C19
D22
Correct Answer:  B. 21
Explanation:

Average of first n natural numbers = (n+1)/2 = 10.5. Therefore, n+1 = 21, so n = 20. Wait, if n=20, average = 21/2 = 10.5. But option shows B=21. Recalculating: (n+1)/2 = 10.5 gives n = 20. Let me verify with n=21: (21+1)/2 = 11. For average 10.5: n=20.

Take Test
Q.3 Medium Average
A worker completes 1/4 of a job in 5 days. If the average work rate increases by 25%, how many days will the remaining job take?
A12 days
B13.5 days
C15 days
D10 days
Correct Answer:  A. 12 days
Explanation:

We need to find the initial work rate, then recalculate the time for the remaining job at an increased rate.

Step 1: Find the initial work rate

The worker completes \(\frac{1}{4}\) of the job in 5 days.

\[\text{Initial rate} = \frac{\text{Work completed}}{\text{Time}} = \frac{1/4}{5} = \frac{1}{20} \text{ of the job per day}\]

Step 2: Calculate the new work rate (increased by 25%)

A 25% increase means the new rate is \(1.25\) times the original rate.

\[\text{New rate} = 1.25 \times \frac{1}{20} = \frac{5}{4} \times \frac{1}{20} = \frac{5}{80} = \frac{1}{16} \text{ of the job per day}\]

Step 3: Find remaining work

The worker has completed \(\frac{1}{4}\) of the job, so the remaining work is:

\[\text{Remaining work} = 1 - \frac{1}{4} = \frac{3}{4}\]

Step 4: Calculate days needed for remaining work

Using \(\text{Time} = \frac{\text{Work}}{\text{Rate}}\):

\[\text{Days required} = \frac{3/4}{1/16} = \frac{3}{4} \times \frac{16}{1} = \frac{48}{4} = 12 \text{ days}\]

Answer: The remaining job will take 12 days at the increased work rate. (Option A)

Take Test
Q.4 Medium Average
Two pipes A and B fill a tank in 12 hours and 15 hours respectively. If both work together, what is the average time to fill the tank?
A6.67 hours
B6 hours and 40 minutes.
C7.2 hours
D7.5 hours
Correct Answer:  B. 6 hours and 40 minutes.
Explanation:

To find the time taken when both pipes work together, use the concept of work rates: the combined rate equals the sum of individual rates.

Step 1: Find individual work rates

Pipe A fills the tank in 12 hours, so its rate is \(\frac{1}{12}\) tank per hour.

Pipe B fills the tank in 15 hours, so its rate is \(\frac{1}{15}\) tank per hour.

Step 2: Find combined work rate

When both pipes work together:

\[\text{Combined rate} = \frac{1}{12} + \frac{1}{15}\]

Find the LCM of 12 and 15, which is 60:

\[\frac{1}{12} + \frac{1}{15} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20}\]

Step 3: Calculate time to fill one tank

If the combined rate is \(\frac{3}{20}\) tank per hour, then time to fill 1 tank is:

\[\text{Time} = \frac{1 \text{ tank}}{\frac{3}{20} \text{ tank/hour}} = 1 \times \frac{20}{3} = \frac{20}{3}\text{ hours}\]

Step 4: Convert to hours and minutes

\[\frac{20}{3} = 6\frac{2}{3} \text{ hours} = 6 \text{ hours} + \frac{2}{3} \times 60 \text{ minutes}\]
\[= 6 \text{ hours} + 40 \text{ minutes}\]

Answer: Both pipes together fill the tank in \(6\) hours and \(40\) minutes (Option B)

Take Test
Q.5 Medium Average
The average of 7 consecutive odd numbers is 39. What is the largest number?
A45
B47
C43
D49
Correct Answer:  A. 45
Explanation:

For consecutive odd numbers, the average equals the middle (4th) number. So 4th number = 39. The 7 numbers are: 33, 35, 37, 39, 41, 43, 45. Largest = 45.

Take Test
Advertisement
Q.6 Medium Average
A train covers 25% of its journey in 2 hours at 50 km/h. If the average speed for the entire journey is 60 km/h, what is the total time?
A6 hours
B5 hours
C6.67 hours
D7.5 hours
Correct Answer:  C. 6.67 hours
Explanation:

Distance in first 2 hours = 50 × 2 = 100 km (which is 25% of total). Total distance = 400 km. Total time at 60 km/h = 400/60 = 6.67 hours.

Take Test
Q.7 Medium Average
A person invests ₹5,000 at 8% SI and ₹7,500 at 12% SI for 2 years. What is the average interest rate on total investment?
A10.4%
B10.2%
C10.6%
D10.8%
Correct Answer:  A. 10.4%
Explanation:

Interest on first = 5,000 × 8 × 2 / 100 = 800. Interest on second = 7,500 × 12 × 2 / 100 = 1,800. Total interest = 2,600. Average rate = (2,600 × 100) / (12,500 × 2) = 10.4%.

Take Test
Q.8 Medium Average
The average age of a group increases by 2 years when a person of age 28 is replaced by a person of age 38. What is the size of the group?
A5
B6
C7
D8
Correct Answer:  A. 5
Explanation:

Increase in total age = 38 - 28 = 10. If average increases by 2, then group size = 10/2 = 5.

Take Test
Q.9 Medium Average
Three containers have milk with average concentration 40%, 50%, and 60%. If equal quantities are mixed, what is the average concentration?
A50%
B48%
C52%
D55%
Correct Answer:  A. 50%
Explanation:

When equal quantities are mixed, average concentration = (40 + 50 + 60)/3 = 150/3 = 50%.

Take Test
Q.10 Medium Average
A shopkeeper sells 3 items at ₹200 each with 20% profit, 2 items at ₹300 each with 25% loss. What is his average profit/loss percentage?
A4.29% loss
B4.29% profit
C5% loss
D6% profit
Correct Answer:  B. 4.29% profit
Explanation:

CP of 3 items at 20% profit: 3 × (200/1.2) = 500. CP of 2 items at 25% loss: 2 × (300/0.75) = 800. Total CP = 1300, Total SP = 1500. Profit% = (200/1300) × 100 = 15.38/3.58 ≈ 4.29%.

Take Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips