Q.21 Hard Power Systems
The critical clearing time in transient stability refers to:
A Maximum time for fault removal to maintain system stability
B Time taken to clear the fault completely
C Time constant of the generator
D Duration of relay operation
Correct Answer:  A. Maximum time for fault removal to maintain system stability
EXPLANATION

Critical clearing time is the maximum duration a fault can exist before the system loses synchronism and becomes unstable.

Test
Q.22 Hard Power Systems
The swing equation in power system stability is given by:
A M(d²δ/dt²) = P_m - P_e - D(dδ/dt)
B M(d²δ/dt²) = P_e - P_m + D(dδ/dt)
C d²δ/dt² = (P_m - P_e)/J
D dδ/dt = (P_m - P_e)/M
Correct Answer:  A. M(d²δ/dt²) = P_m - P_e - D(dδ/dt)
EXPLANATION

The swing equation relates angular acceleration to net mechanical power (P_m), electrical power (P_e), and damping coefficient (D).

Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips