Home Subjects Electrical Engg (EEE)

Electrical Engg (EEE)

Electrical machines, power systems, circuits

321 Q 7 Topics Take Mock Test
Advertisement
Difficulty: All Easy Medium Hard 241–250 of 321
Topics in Electrical Engg (EEE)
Q.241 Medium Power Systems
In a 400 kV transmission line, if the sending end voltage is 400 kV and receiving end voltage drops to 380 kV, what is the percentage voltage regulation?
A 5%
B 4.76%
C 5.26%
D 4.5%
Correct Answer:  C. 5.26%
EXPLANATION

Voltage regulation = [(VS - VR) / VR] × 100 = [(400 - 380) / 380] × 100 = 5.26%

Test
Q.242 Medium Power Systems
What is the primary function of phase-shifting transformers in Indian grid operation?
A To control power flow direction and magnitude on interconnected transmission lines
B To reduce transformer core losses
C To eliminate harmonic distortion
D To provide frequency stabilization
Correct Answer:  A. To control power flow direction and magnitude on interconnected transmission lines
EXPLANATION

Phase-shifting transformers control power flow by introducing a phase shift between primary and secondary voltages, enabling effective power flow management on parallel transmission corridors in Indian grid.

Test
Q.243 Medium Power Systems
In selective fuse coordination, which fuse should operate first during a downstream fault?
A The fuse closest to the source
B The fuse closest to the fault location
C All fuses simultaneously
D The largest fuse in the system
Correct Answer:  B. The fuse closest to the fault location
EXPLANATION

Selective coordination requires the fuse nearest to the fault to operate first, isolating only the faulted section while maintaining service to other areas.

Test
Q.244 Medium Power Systems
What is the primary purpose of a phasor measurement unit (PMU) in modern Indian grids?
A Measuring harmonic distortion only
B Real-time monitoring of voltage/current phasors with synchronized timestamps
C Temperature sensing in transformers
D Reactive power compensation
Correct Answer:  B. Real-time monitoring of voltage/current phasors with synchronized timestamps
EXPLANATION

PMUs measure voltage and current phasors synchronized via GPS, enabling real-time monitoring and control. India has deployed PMUs across POWERGRID network for situational awareness.

Test
Q.245 Medium Power Systems
In voltage stability analysis, what does the P-V curve represent?
A Relationship between real power and voltage at a load bus
B Relationship between reactive power and voltage
C Frequency variation with power
D Impedance versus voltage profile
Correct Answer:  A. Relationship between real power and voltage at a load bus
EXPLANATION

P-V curves show how voltage varies with increasing active power at a bus. The nose point indicates the maximum power that can be transmitted before voltage collapse.

Test
Q.246 Medium Power Systems
What is the relationship between power factor and reactive power in a 3-phase system?
A Q = P × tan(φ)
B Q = P / tan(φ)
C Q = P × cos(φ)
D Q = P × sin(φ) / cos(φ)
Correct Answer:  A. Q = P × tan(φ)
EXPLANATION

Reactive power Q = P × tan(φ), where φ is the phase angle between voltage and current. This fundamental relationship determines VAR compensation requirements.

Test
Q.247 Medium Power Systems
What is the economic dispatch problem in power systems?
A Allocating available power to minimize total generation cost while meeting demand and constraints
B Distributing power equally among all generators
C Maximizing reactive power generation
D Reducing transmission line losses only
Correct Answer:  A. Allocating available power to minimize total generation cost while meeting demand and constraints
EXPLANATION

Economic dispatch optimally allocates power generation among committed units to minimize fuel costs while satisfying load demand and operational constraints.

Test
Q.248 Medium Power Systems
In a 3-phase balanced fault at a bus, what is the fault current expression for a synchronous generator?
A V/Xd''
B V/(Xd' + Xd'')
C V × Xd''
D V/(2Xd' - Xd'')
Correct Answer:  A. V/Xd''
EXPLANATION

Subtransient reactance (Xd'') is used immediately after fault occurrence. Fault current = V/Xd'' for a 3-phase symmetrical fault at the generator terminals.

Test
Q.249 Medium Power Systems
Which protection scheme is typically used for protecting transmission lines in Indian grid?
A Overcurrent protection only
B Distance protection (impedance relay)
C Differential protection only
D Thermal protection only
Correct Answer:  B. Distance protection (impedance relay)
EXPLANATION

Distance relays provide selective protection for transmission lines by measuring impedance from relay location to fault point, standard in Indian POWERGRID.

Test
Q.250 Medium Power Systems
What is the primary advantage of using HVDC transmission over HVAC for long distances?
A Lower cost of cables
B Easier protection coordination
C Reduced transmission losses and no reactive power issues
D Better short-circuit capacity
Correct Answer:  C. Reduced transmission losses and no reactive power issues
EXPLANATION

HVDC reduces I²R losses (proportional to current squared) and eliminates reactive power flow, making it ideal for long-distance bulk power transmission.

Test
IGET
IGET AI
Online · Exam prep assistant
Hi! 👋 I'm your iget AI assistant.

Ask me anything about exam prep, MCQ solutions, study tips, or strategies! 🎯
UPSC strategy SSC CGL syllabus Improve aptitude NEET Biology tips